Resurfacing work along the Island’s Main Road here on Nevis (from Walcos to Rams) and Pump Road (from the Roundabout to Club Trenim) is completed.
The work began on Monday, February 8th and was completed in almost two (2) weeks, in two phases.
Phase 1 was the removal of the old Asphalt and Phase 2, included the Asphalt resurfacing of the above-mentioned areas.
Director of the Public Works Department here on Nevis, Mr. Jevon Williams tells us more:
Mr. Jevon Williams.